Case Study: Office Refurbishment and Fit Out in West Yorkshire

Location:Leeds, West Yorkshire

Building:2-storey office unit

Date:August 2020-September 2020

The transformation of a commercial 2 floor office space. Both floors required a complete overhaul of the existing interiors, with removal of the existing partitioning, flooring, ceiling, kitchen and WC’s before the new installation commenced. 

The Design Brief

Rodley Interiors Ltd were contacted by a new client in Leeds, West Yorkshire to transform their existing workspace which they held over 2 floors. The Office Refurbishment and Fit Out project included a complete overhaul of the redundant and un-inspiring offices. Our brief was to create bright and open plan style offices which would enable our client to have the scope to move their office furniture and teams to suit their changing needs when staff begin to return to work.

  • The project was completed with a quick turn-around time of 6 weeks
  • Project value £45,000.00 including free site survey, quotation, and aftercare service.

Office Refurbishment and Fit OutOffice Refurbishment and Fit OutOffice Refurbishment and Fit Out

Project Specification and Installation Details

  • Strip out of the existing interiors
  • External Shutter Installation
  • Power and data works
  • Flooring including feature office carpet tiles and vinyl and safety flooring to the Kitchen and WC areas
  • Suspended ceiling installation
  • LED office lighting
  • Office Partitioning
  • New office kitchens
  • WC and facilities
  • Painting and decoration works
  • Office fire door installation
  • CCTV installation
  • Roofing works including deep clean and re-pointing
Office Refurbishment and Fit Out

 

If you are based in Leeds or West Yorkshire and require Office Refurbishment and Fit Out works to your workspace and for more information on this transformation project do not hesitate to contact us today…