Client:Witheld
Location:Birmingham
Industry:Commercial Letting Agents
Building:Contemporary office building
Date:July 2016 - August 2016
Rodley Interiors helped make the most of the natural light with glass office partitioning. The works were in keeping with other partitioning installations we have carried out for our client nationwide.
The Design Brief
Rodley Interiors were invited to carry out a glass office partitioning project in Birmingham for an existing client. The floor space already had the benefit of large external windows, so maximising the light that these let through was something our client wanted to focus on. The office partitioning that we installed created;
- Meeting rooms
- One to one areas
- Kitchen areas
During the planning of the project we wanted to install a partitioning system that would be both practical and fit in with our clients requirements.
Glass office partitioning to utilise natural light
To continue the fluidity of light from the large external windows we fitted frameless glass partitioning. The glass offices looked modern and contemporary and complimented the rest of the install. Frameless glass partitioning is the an ideal way to divide a space whilst still maintaining the feel of openness and light.
Corporate company partitioning
Following on from the other partitioning projects we have carried out for our client, we have fitted frameless glass office partitioning to match. We have installed frameless glass panels in conjuction with Walnut feature doors.
The white clean framework complements the glass partitioning well and allows for bright look throughout. The offices were finished with a deep blue band of manifestation film.
The manifestation film is applied directly to the glass after it has been fitted. The bright blue film has an opaque finish and still lets light through to the office space.
Walnut doors create a real contrast to the clean glass office partitioning giving the ‘wow’ factor.
Additional works to the floor space
- Strip out works
- Urban retreat carpet tile install completed over 3 phases.
- New kitchen works
- Works to the existing tea point area.
- New suspended ceiling tiles.
- Painting and decoration works.
- Electrical and data cabling works